To, Date:-31/03/11
SDO
Metering Deptt.
DHBVN OFFICE
Gurgaon (HR)
SUBJECT: - H.T. Line Jumpher Wire Short and Burnt Out Due to Heavy Strom & H.T. Line Insulator Hanging in Air at 1:45 am MID Night on 29/03/11 .
Dear Sir,
Kindly Note that 29/03/11 Mid Night our H.T. Line G.O. Switch Jumpher wire burnt out due to Short Circuit occurs by Heavy Strom.
We have Complained on 66 KV Sub-Station at 8:00 AM and follow-up to Sub-Station JE (Mr. Naseem Ahmed) & Line Men for Repairing from 9:00 AM to till regularly on 30/03/11.
Today (31/03/11) Also We have to Complained on 66KV Sub-Station Regarding above Matter, but No Any Persons attended the Problems.
So Please Check Also on Your end because he will say that’s Problems occurs by Metering CT’s & PT’s, while One H.T. Line Insulator are Hanging in Air Freely of Blue Phase & Red Phase Insulator not Available and Our Internal GO Switch Fuses are OK, But All Persons are not Agree.
Sir, Our Plant are Running on Captive Power Last Two Days that is very expansive .So we are request you please attend the problem and resolved it as soon as possible.
Account No. - G31 CYCCODE: HI
Old Account No.:- SPHT – 0004
Meter Sr. No.:- ILS-3
Thanking You
Your Faithfully
For Jay Ushin Ltd.