Address: | Gurgaon, Haryana, 110029 |
My Flat Tower 4 .1603
Have paid everything except the last instalment.
The project is delayed almost 8 years
I have seen the tower physically.I was told the fire certificate was a problem -and that the certificate was received.
Consumer Care does not answer
They tell lies- sorry to say so.
Soni Srivastava gave a deal on phone that they will deduct some money from the balance payable ( currently with penalty - they would need to pay me) and I can take possession and get the full flooring, plumbing etc done .She said she cant give it in writing.
I asked for a written letter of offer - but she refused- after that she refused to answer.
I just need all the documents and the possession - with the penalty paid and deduction of market cost for getting the job done ASAP.
[protected]@yahoo.com ; [protected] / [protected] Was this information helpful? |
Post your Comment