All India Council For Technical Education [Aicte] — Grant final instalment not given | |||
In 2013, AICTE has approved the following Project to PSN College of Engineering and Technology, Mela Thediyur, Palayamkottai Taluk, Tirunelveli District, Tamil Nadu. PIN : 627152. The first installment amount was remitted in 2013. The second and final installment amount is not remitted. It is long overdue. Project : Industry Institute Partnership Cell (IIPC) a) Ref No : F.No 14-14/RIFD/IIPC/POLICY-1/2013-14 b) Sanctioned amount : Rs 6.5 Lakhs c) First installment received : Rs 4.5 Lakhs on 13/8/2013 d) Project Period : 2013 to 2014. e) Project Completion Report (Annexure –V) sent on 26th March 2015 f) Sanction and remittance order for the release of Rs 2 Lakhs (second and final installment) dated October 2015 by Shashikant .P. Borker, Adviser (RIFD). g) The amount of Rs 2 Lakh is Not received till today the 23rd June 2016 Was this information helpful? | |||
| |||
3 Comments | |||
Comments
In both cases, Modernisation of Power Systems Simulation Laboratory (MODROBS) and Industry Institute Partnership Cell (IIPC) for PSN College of Engineering & Technology, Between 2014 and 2015,
A) At least 5 follow up letters were sent to get the 2nd and final instalment of the grant.
B) The public relations officer of PSNCET talked personally many times, to the AICTE contact personnel.
But, there was no replies or response or action to send the balance payments.
A) At least 5 follow up letters were sent to get the 2nd and final instalment of the grant.
B) The public relations officer of PSNCET talked personally many times, to the AICTE contact personnel.
But, there was no replies or response or action to send the balance payments.
1) In both cases, Modernisation of Power Systems Simulation Laboratory (MODROBS) and Industry Institute Partnership Cell (IIPC) for PSN College of Engineering & Technology, the final instalment was due in mid 2015.
2) consumer complaint was lodged on 23rd June 2016.
3) First comment for no action was made on 4th July 2016.
4) There is no action or communication from AICTE till today the 16th July 2016
AICTE, controlling and monitoring the graduate and post graduate education in India, should not be a sleeping body like this !!!. There is no Creativity and Action orientation in AICTE.
2) consumer complaint was lodged on 23rd June 2016.
3) First comment for no action was made on 4th July 2016.
4) There is no action or communication from AICTE till today the 16th July 2016
AICTE, controlling and monitoring the graduate and post graduate education in India, should not be a sleeping body like this !!!. There is no Creativity and Action orientation in AICTE.
27%
Complaints
180
Pending
0
Resolved
48
+91 33 2335 2445
LB Block, Sector III, Salt Lake City, Bidhannagar, Saltlake, India - 700098
Modernisation of Power Systems Simulation Laboratory (MODROBS)
a) Ref No : 12/AICTE/RIFD/MOD(Policy-4)Pvt-70/2012-13
b) Total Amount sanctioned – Rs 10 Lakhs on 13/6/2013
c) Amount remitted – Rs 8 Lakhs on 13/6/2013
d) Actual incurred for the project – Rs 9, 94, 236
e) Project completion report sent on – 16/4/2014
f) Balance due to be received : (Rs 9, 94, 236 – Rs 8, 00, 000) = Rs 1, 94, 236
g) The amount is Not received till today the 23rd June 2016