I have a flat booked in silicon city sec-76, project since september 2011 in tower-z.
Till now the building works are not finished and there is no sign of finishing and handingover of the flats.
Since last one year there is no progress.
1. Lifts are not delivered & installed.
2. Plumbing work is pending.
3. Fire fighting work is pending.
4. Electrical works are pending.
5. Flooring is pending in flats & staircase.
6. Internal finishing works - doors, windows, woodwork is pending.
There is no progress of work.
Mr. Anil sharma (Md of amrapali) has comitted in his tv interview that he will positively give posession by december-2016.
But he has also failed in his comittments.
Can anyone ensure when will this project be completed and we can get our flats.
Deepak sharma