GIFT City Construction Progress - April 2018
GIFT City - India’s 1st Under Construction Smart City on the bank of the river Sabaramati near Gandhinagar, Gujarat.
Left to Right: Signature Tower, GIFT One Tower, GIFT Two Tower, Brigade Tower (Under Construction), World Trade Center (Under Construction)
IFT City Completed Buildings:
GIFT One Tower in DTA - 28 Storey :: Occupancy 80% :: Major Tenant IT, BPO, PSU, Banking, Oracle, Maxim Integrated, bfree
Left to Right: GIFT One Tower & GIFT Two Tower in GIFT City, Gandhinagar, Gujarat.
Photo Credit: News, Updates, Construction Progress for WTC GIFT City, Gujarat
2. GIFT Two Tower in DTA - 28 Storey :: Occupancy 30% :: TCS has acquired 3 floors out of 28 floor, Infibeam has Started Operations on 3 floors, Interior & Furniture Work for 3 floors going on for TCS & their associates
3. Jamnabai Narsee International School in DTA - 5 Storey - 1 to 7 Standard 600+ Students
4. TCS Tier 4 Data Center in DTA- 3 Storey :: Operational
5. Hiranandani Signature Tower in IFSC - 16 Storey :: Occupancy 15% :: Major Tenant - BSE INX has acquired 1 st Floor. Kotak Mahindra and Other Banks are planning to Acquire other floors
On Right: Signature Tower in GIFT City Gandhinagar, Gujarat.
Photo Credit: News, Updates, Construction Progress for WTC GIFT City, Gujarat
6. Aspire One - Incubation Center in IFSC - 3 Storey
7. Aspire Two - Incubation Center in IFSC - 3 Storey
DTA = Domestic Tarrif Area
IFSC = International Finance Service Center (FINANCE /IT SEZ)
GIFT City Under Construction Buildings:
World Trade Center GIFT City :: 4 towers Under Construction :: Construction Pace - Slow
Tower A: 6/6 floor Slabs casted
Tower B: 23/28 floor Slabs casted
Tower C: 0/18 floor Slabs casted
Tower D: 6/6 floor Slabs casted
2. Janadhar Mangala :: All towers under construction : Expected Possession 2018 :: Affordable Housing :: Construction pace - Good
3. Brigade tower in IFSC : structure of entire tower completed : Facade and services work going on. Expected Possession Q3 - 2018 :: Construction Pace - Fast
4. Brigade IBIS Styles Hotel in DTA : 10th floor slab casting in progress :: Expected Possession Q4 - 2018 :: Construction Pace - Fast
5. Gift International Center : Business Club: Structure work Completed : Some portion of the club will start soon. Construction Pace : OK
6. Savvy ATS tower in IFSC: Basement level work completed. 3rd floor slab casting in Progress.
Non Starters:
SBI Tower : Plot Allotted in 2014 : Construction Work not Started Yet - Bhoomi Poojan was in SEPT 2017
BSE Brokers Forum Tower: Plot Allotted in 2014: Construction Work Not Started Yet - Bhoomi Poojan was in March 2018
LIC: Plot Allotted in 2015: Construction Work Not Started Yet
Reliance (ADA): 2 Plots Allotted in 2016: Construction Work Not Started Yet
BU Bhandari Projects Pune: Plot Allotted in 2014 : Construction Work not Started Yet
Sterling Hospital: Plot Allotted in 2014: Construction Work not Started Yet