Address: | 1-161, thummalcheruvu, piduguralla , guntur AP 522437 |
HI this is Rajasekharreddy Dodda I'm from thummalcheruvuu, actually, I applied for an 11 kV industrial line for a bricks factory (amma hollow bricks) last year in October 2021 and the estimate is sectioned on Feb month 2022 then after I had paid the estimated amount online. He (ADE) operation was says to me the estimate will be revised because material prices increased in march month, I agreed and also I had to pay the balance resived amount on April month, he said the process is completed, he said to me, I will draw the material in store, ok please continue fast sir I said, Poles are draw that and erected . my line is not complete line forming yet. In the last three months he doesn't respond properly, the phone is not receiving and the last one I felt go to the ADE office meet once, 5 times I had goes the office, he was not there and he wasn't answering my phone yet. ADE number [protected] Was this information helpful? |