[Resolved]  RAUNAK GROUP (Thane) — Delay in construction

Address:Thane, Maharashtra

Hi ,

I have booking in (under construction) 2BHK flat in Raunak Group's Unnathi woods Phase Ii project.

I had booking in FEB 2009 and booing suppose to be june, 10 . subsequently to

On agreement it was Dec 2010, stating will be adding further 4 storey )12

The construction is very very Pathetically slow, till date only 4 Storey s are constructed.

I am really worried at his pace It will take 5 years. I tired visitng Builders office everytime he gives different excuse, On request to cancel he does not allow to cancel.
I suggested if want to sell to other he states he won't issue NOC even if issue he will charge Exorbitant amount which is really emotionally depressive.

There is Cement problem, Labour problem however in the same locality other builder are carrying out work at descent . It seems the builder is careless, reluctant to listen our plead.

Currently I am leaving on rent finding a new house in mean time has become costly and depressing affair

Kindly advice how to cope this situation. What action can be taken against builder so that he expediate the construction and handover my dream home.

Where to contact and make complaint a
Was this information helpful?
No (0)
Yes (1)
Aug 13, 2020
Complaint marked as Resolved 
Complaint comments 

Comments

now it is dec 2011
Yes I am completely agree with you. They have another project called unnathi greens in the same locality, wherein at the time of sale they told that possession will handed over by aug sep 2010, now its november but still no idea of when will we get our flats. Also quality of construction is very bad, cable point is fixed where there should be telephone point and telephone point is fixed at cable point.
I am experiencing the same problem and feedback is irrelevant and i am also residing on the rental basis, some action to be initiated on the defaulters
Yes, i do agree with you guys, i have also booked a flat in Unnathi Woods Phase V in Jan 09. While booking it was told that possession will be getting in Jun 10 which is also mentioned in the agreement. But still i am looking for possession & it is expecting by this month end. I am also staying in a rented flat.

The worse part is i wanted to sell it off, since possession was getting delayed but builder was asking Rs. 700 per sq.ft. for giving NOC.

I am also frustrated just because of this. Any idea if we can take any action against this? please share it if anyone has got it.
Hi All,

I have also booked a flat in Unnathi Woods, A4 - 102, Name : Upendra H Nadgaonkar. Have already uploaded my complaint on this site.

Can we all get together and take action against this.

Number - [protected]
Hi All,

I have also booked my flat in Unnathi Woods Phase 2. The possession of the flat has been delayed by 1.5 years and still the arrogant, unfriendly customer attitude of Raunak Group continues. There is no point just writing complaints on this website and doing nothing. A support Upendra suggestion to get together and file complaint against RAUNAK GROUP. Iam already doing so.

My contact number is [protected]
Email id is vishalgarg.[protected]@gmail.com

Would request all to wake up and let RAUNAK GROUP know consumers cannot be exploited.
Hi Upendra and Vishal,

I agree with both of you. We should get together and file a case in consumer court. My flat is in Phase I, A6. The builder is giving the same reason for last 6 months saying that he has not got the OC. Every time I call his office or meet the concerned person, I am being told that the possession would be given in a few days time. Recently I was told that possession will surely be given by 15th Nov 2011 and then when the date came, he said that still the OC has not come and he will give the possession definitely by 30th Nov 2011. However when I called him up yesterday, I was told that 30th Nov would not be possible as the OC has not yet come. He is saying that in Thane Munical Corporation, the person who gives OC is available only on Tuesdays and that too he is very busy so it is very difficult to meet him. I am fed up of all such stories. Now I am told that he will give possession in next 10 days, however I know that after 10 days he will make some other story and say that OC has not yet come.

We should get together in maximum numbers and go to consumer court and file a very strong case against this builder. He is cheating all the customers. Infact he has taken the money from all the customers and is building the new project in Kalyan with this money. He is not bothered about this project as it is already sold out, whereas he has to sell the project in Kalyan. We should ask the court to force the builder to pay us the interest money on the amount paid to him. He should also pay us compensation for the mental torture that he is putting for so long now.

Lets meet at his office and take this further. All those who are victims of this Raunak Group Builder (Unnathi Woods), Please call me on [protected]. Lets all make a big group and the impact in the court will be very strong.

Aliasger Chasmai
[protected]
[protected]@gmail.com
Hi Vjameta, sac_rauthan, jagtap dilip s, yeole pankaj request you all to share your details ( Phone Numbers, Email ids) we all need to group together and as suggested by Aliasger, Upendra and myself need to file a GROUP CONSUMER COMPLAINT against RAUNAK GROUP. Its high time these builders need to be woken up, there arrogance, unfriendly attitude towards customers and delaying tactics need to be put to end.


We must demand in WRITING EXACT POSSESSION DATE, COMPENSATION ( both in terms of monetary and mental torture) FOR THE DELAY FROM ORIGINAL POSSESSION DATE.


Regards
Vishal

Post your Comment