Address: | Mumbai Suburban, Maharashtra |
We have power failures in our building twice in a fortnight. One phase o[censored]nder ground cable was declared faulty and Reliance men provided supply through temporary overhead flexible wire along with two phases of main cable. Second time after approx. 12 days time, second phase too failed and again they provided supply by laying one more flexible over head wire (not cable).
With third phase which can also fail, we will have supply through three flexible wires to our building. Reliance men were requested for providing power through underground permanent cable and complaints were too lodged. So far after 20 days time, there are no actions taken.
D.L.Rambhia
42, New Rajshree Dham CHS Ltd.,
Jagdusha Nagar,
Ghatkopar West,
Mumbai 400086
[protected] Was this information helpful? |
We request to you shortly solved the problem.