Myself Anupam Sharma is one of, Exploited customer Ansal Housing Plam Court Jhansi project. I had booked one 2 BHK flat (E- 502) in AUG 2011 in Ansal Palm Court Jhansi and it was promised to me that the possession will be somewhere in between mid of 2014. When after Oct 2014 it was not delivered I contact again Ansal team and they told us that it will be delivered Now Mid of Next year (2015). Now this duration is also passed it is not delivered to me. In between, I had contacted the Ansal Team (Hridesh & Sushil) member and surprise to know that both are left the company. Because I didn’t live in Jhansi so I can’t get contact with your new team unless I visited again. And as per you new team even the Ansal in nowhere ready to deliver my flat even End of this year. As per them, it will deliver next year but they even don’t know when. I had paid almost all money (except 5 %) and even today I had no clue that when I t will be delivered.
I had server money crisis due to this, all my investment are stuck due to this. I had several others complain which I want to address with your team.

On 21 st Oct 2015 they promise me again that possession will be done Jan-Feb 2016 but this date was again passed.

Below is that email for same.

*****************************************************************

ROHIT KUMAR
10/21/15

to me, Customerconnect

Dear Mr. Sharma

Warm Greetings!

This has reference your allotment for the said unit, we wish to inform you that the development of the site is in progress.
We are scheduling to offer possession of the E-tower around Jan-Feb 2016 subject to force majeure circumstances.

For any further communication regarding your concerns, please email us at [protected]@ansals.com.

Assuring you of our best of services,

Regards,
Rohit Kumar

CustomerConnect Team
Ansal Housing & Construction Ltd.
*****************************************************************************

I reminded him again and they replied after 30 days on 19 May 2016 that possession will be done within 3 months.
but again i waited till august and September and they didn't offer the possession.
********************************************************************************...

Customerconnect
May 19

to me, ROHIT

Dear Sir/ Madam

Warm Greetings!

With reference to your query pertaining the possession of said flat, it would take 3 more months to scheduling the offer of possession. For any further communication regarding your concerns, please email us at [protected]@ansals.com.

Assuring you of our best of services,

*****************************************************************************

I had taken picture of my flat 3-4 month back picture is also attached with the complaint to see the status of my project.

Regards
Anupam Sharma
+6 photos
Was this information helpful?
No (0)
Yes (0)
Complaint comments 

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Jhansi
    Uttar Pradesh
    India
    File a Complaint