[Resolved]  Sbs Enterprises. Pune — cbi enquiry at garrison engineer girinagar pune against corruption in mes

Address: L 706, Sapphire Park, Park Street, Wakad,, Pune, Maharashtra, 411057

I am sanadip s sarkar, working partner of m/s sbs enterprises, pune. M/s sbs enterprises is central govt. Enlisted contractor in military engineering services.
Since 2012 we are working to eliminate corruption in mes.
We raised the complaint for syphoning nearly 50 lakhs of govt. Money by shri tapan kumar nayak, garrison engineer (I) girinagar pune under chief engineer r&d secunderabad on dated 03 july 2018, but chief engineer r&d secunderabad shri anand srivastava was reluctant to take necessary corrective action against ge shri tapan kumar nayak. Reason may be under the influence of vested interest.
Cbi pune branch has initiated an site enquiry at defence institute of advanced technology, girinagar on 30 and 31august 2019.in this regard cbi has seized all documents from ge office and taken all sample from site for their further routine enquiry.
I may request you to publish the news to make indian citizen aware that corruption should not be supported by all.
If you feel to publish such news in your news paper or channel and if you require any further details, we please may be contacted on [protected]/[protected].
Thanks and regards
Sarkar
L 706, sapphire park, park street, wakad,
Pune 411057
Was this information helpful?
No (0)
Yes (0)
Sep 7, 2019
Complaint marked as Resolved 
It is under scrutiny of CBI Pune, not yet resolved but in process.
Sep 07, 2019
Updated by Sanadip Sarkar
MY ORIGINAL COMPLAINT as bellow:-

S B S Enterprises Ph.[protected] / [protected]
MANUFACTURERS ELECTRICALS CONTROL PANELS DISTRIBUTION, MCC, PLC, AMF. Dealing in Cummins, KOEL, & Greaves Diesel Generating sets. (5 KVA to 1250 KVA) Email:sbsgroup.[protected]@gmail.com L 706 SAPPHIREPARK PARKSTREET WAKAD PUNE 411057.
Ref: SBS/COR/01/18-19 -1- Dated 03/07/2018
To,
Shri Anand Srivastava Chief Engineer R&D Military Engineering Services Opp. Jubilee Bus Station Picket, Secunderabad 500003
Sub: - NEARLY 50 LAKHS OVERPAYMENT TO THE CONTRACTOR BY GE/AGE
1. Name of Contract: - Conversion of HT O/H Line into underground 22 KV cable at Girinagar.
2. Name of Contractor: - M/s Ganesh Enterprises.
3. CA No: - CERD/GIR/ 45 of[protected]
Dear Sir,
With Reference to the above subject, I would like to raise some points of wrong doing by Shri Tapan Kumar, Garrison Engineer Girinagar Pune, for your knowledge and necessary strict action. Which may be or may not be for any vested interest but surely it is giving some undue financial to contractor by misusing his assigned Power.
The contractor has been allowed by GE to take his RAR around 3 crore, which around 95% of Contract amount on 27 June 2018.
Few points o[censored]ndue advantages given to contractor as bellow;
1. Working is still in progress – Attaching few photos for your ready references.
2. Only laying of cable is completed.
3. Depth of trench neither as per SSR Part I 2009 clause No 19.74.1 i.e. 1 mtr, whereas MB recorded .6 mtr depth and .45 mtr width.
4. Also method of laying is not followed as per SSR Part I 2009 clause No 19.75 nor as per any Engineering practice.
5. As per CA provision supply, laying commissioning and testing, cable has been laid without bottom layer of sand of 8cm.



-2-

6. Crushed sand has been used instead of River Sand, when there is no deviation in writing by the accepting officer then how GE can violate CA provision, must be enquire. If there is such deviation please let me know to correct my observation.
7. Cable covers are till 02 July 2018 laying at site in open area but not placed in trench till date and GE accepted complete work done and paid accordingly.
8. Most of the places double runs cable laid in the same .45 mtr trench without but spacing is not 25 to 40 cm as recommended in SSR Part I 2009 clause No 19.76
9. Panels are kept aside in open places not yet installed and few panels are just installed but not connected because cables laying are still in progress. Failed to understand how it can be passed in RAR with 100% work done by restriction nominal percentage for testing.
10. The cable joints are not paid then how only cable laying can be paid full amount in work done.
11. Surprisingly this contract is going under the very nose of GE and AGE still how contractor has been allowed to execute the work not as per specification. Hope this mal practice of execution of contract made GE and AGE to close their eyes under the influence of vested interest of GE and AGE to get the undue benefits.
12. I being tax payer of INDIA and esteemed citizen of INDIA may have the right to know the interest of GE and AGE to allow contractor for such violation of Gov. Contract which may affect general Indian citizen who are literally striving for a piece of bread for their livelihood.
13. I reserve the right to request you as accepting officer must order special board to enquire the facts which I am forwarding to you with few documentary proof.
14. Your strict action can safe so many things, and surely may help our Nation.
Thanking you,
Yours faithfully

Sanadip S Sarkar
Note: - Twelve snapshot duly marked attached, which are exclusively for site not related with any MES establishment.
CC: -
1. Hon. Prime Minister: - Shri. Narendra Modi - Humble request for your intervention. Email: - [protected]@narendramodi.in / [protected]@mygov.nic.in/ [protected]@gmail.com
2. Hon. Defence Minister: - Smt. Nirmala Sitharaman - Humble request for your intervention. E mail:- [protected]@gmail.com / m.[protected]@nic.in / [protected]@mod.nic.in
3. Engineer-In-Chief :- LT GEN SK SHRIVASTAVA, AVSM :- Humble request for your intervention.
Directorate of Contract Management & Administration
New-Delhi — 11
Email: - [protected]@nic.in
4. Addl. Director General (Of & DRDO) Secunderabad:- Humble request for your intervention.
5. HQ DRDO, DRDO Bhavan ‘A’ Wing Rajaji Marg, New Delhi – 110011
6. Commandant:- At Defence Institute of Advanced Technology:- Humble request for your intervention.
Girinagar, Pune 411025
7. Shri Tapan Kumar- GE Girinagar.
Sep 07, 2019
Updated by Sanadip Sarkar
MY ORIGINAL COMPLAINT TO CBI as bellow:-

S B S Enterprises Ph.[protected] / [protected]
MANUFACTURERS ELECTRICALS CONTROL PANELS DISTRIBUTION, MCC, PLC, AMF. Dealing in Cummins, KOEL, & Greaves Diesel Generating sets. (5 KVA to 1250 KVA) Email:sbsgroup.[protected]@gmail.com L 706 SAPPHIREPARK PARKSTREET WAKAD PUNE 411057.
Ref: SBS/COR/02/18-19 Dated 05/07/2018
To, -1-
Shri M.R. Kadole
(Addl. Charge) HOB
ACB Pune
GPOA, Kendriya Sadan,
A & B Wing, Akurdi,
Pune – 411044
[protected]
[protected]@cbi.gov.in

Sub: - NEARLY 50 LAKHS OVERPAYMENT TO THE CONTRACTOR BY GE/AGE
1. Name of Contract: - Conversion of HT O/H Line into underground 22 KV cable at Girinagar.
2. Name of Contractor: - M/s Ganesh Enterprises.
3. CA No: - CERD/GIR/ 45 of[protected]
Dear Sir,
With Reference to the above subject, I would like to raise some points of wrong doing by Shri Tapan Kumar, Garrison Engineer Girinagar Pune, for your knowledge and necessary strict action. Which may be or may not be for any vested interest but surely it is giving some undue financial benefit to contractor by misusing his assigned Power.
The contractor has been allowed by GE to take his RAR around 3 crore, which around 95% of Contract amount on 27 June 2018.
Few points o[censored]ndue advantages given to contractor as bellow;
1. Working is still in progress – Attaching few photos for your ready references.
2. Only laying of cable is completed.

-2-

3. Depth of trench neither as per SSR Part I 2009 clause No 19.74.1 i.e. 1 mtr, and MB also recorded .6 mtr depth and .45 mtr width as actual.
4. Also method of laying is not followed as per SSR Part I 2009 clause No 19.75 nor as per any Engineering practice.
5. As per CA provision supply, laying commissioning and testing, cable has been laid without bottom layer of sand of 8cm.
6. Crushed sand has been used instead of River Sand, when there is no deviation in writing by the accepting officer then how GE can violate CA provision, must be enquire. If there is such deviation please let me know to correct my observation.
7. Cable covers are till 02 July 2018 laying at site in open area but not placed in trench till date and GE accepted complete work done and paid accordingly.
8. Most of the places double runs cable laid in the same .45 mtr trench without but spacing is not 25 to 40 cm as recommended in SSR Part I 2009 clause No 19.76
9. Panels are kept aside in open places not yet installed and few panels are just installed but not connected because cables laying are still in progress. Failed to understand how it can be passed in RAR with 100% work done by restriction nominal percentage for testing.
10. The cable joints are not paid then how only cable laying can be paid full amount in work done.
11. Surprisingly this contract is going under the very nose of GE and AGE still how contractor has been allowed to execute the work not as per specification. Hope this mal practice of execution of contract made GE and AGE to close their eyes under the influence of vested interest of GE and AGE to get the undue benefits.
12. I being tax payer of INDIA and esteemed citizen of INDIA may have the right to know the interest of GE and AGE to allow contractor for such violation of Gov. Contract which may affect general Indian citizen who are literally striving for a piece of bread for their livelihood.
13. I reserve the right to request accepting officer to order special board to enquire the facts which I am forwarding to you with few documentary proof.
14. Your strict action can save so many things, and surely may help our Nation.
15. In this regard already raised the issue with Chief Engineer R&D Secunderabad and higher authority, but not sure how far they wish to enquire the things against department so called system. Hence keeping high hopes I am sending this case to you for detailed investigation please.
Thanking you,
Yours faithfully

Sanadip S Sarkar Note: - Twelve snapshot duly marked attached, which are exclusively for site not related with any MES establishment.
 
Add a Comment

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Sbs Enterprises. Pune
    L 706, Sapphire Park, Park Street, Wakad,, Pune
    Maharashtra
    India
    File a Complaint