Date 22/06/2016
Lalita s. Gupta
Santosh j. Gupta
104/a dheeraj vishwas,
Natwar nagar road no.1
Jogeshwari east mumbai 400060
Mobile: [protected] / [protected]
To,
Vinay unique developers
Hdil layout sector no 2, global city, chikhal dongre road,
Dongre village, virar west, mumbai, maharashtra 401303
K. Attn: mr. Piush mehta
Mr. Leelesh prakash haldankar /mr. Saleem pasha/ mr. Anup ashok mehta /
Dear sir,
Thank you so much for giving me time to meet you and discuss the issue over the table.
However during our meeting as i explained you that i am in the heavy financial loss due to delay in the possession.
During our communication i insisted you to credit the interest on money paid to you for the delayed period. I still insist on the same & request you to confirm the same ok.
My request is genuine, as all your demand letter sent to me shows that in case if i fail to pay timely i have to pay interest @ 24%,
During our meeting you stated that i too have delayed the payment, please be noted that was based on the agreed payment schedule. Secondly i had booked the flat at plinth level and constructions work was going very slow compare to your promise.
So request you to re-consider your decision & confirm to credit the interest or i am helpless to extent the matter to consumer court.
Looking forward to hearing from you.
Thanks/regards,
Santosh j. Gupta