Dear sir,
We are from annur taluk, anbu nagar area. Last 3 days a huge power cut happend. We thought of some maintenance work in progress.
Now the problem is total power shut down almost 30 hours. May 28, 2020 power cut started & till now no power in my area. No response from anyone.
When we call eb office nobody pick the call. Few people said couple of poles damage during rain.
At the same time annur town, a big tree fell down and with in 4 hours issue got fixed. Why not fixed our area?
Not only this time. We are frequently facing this issue with eb folks eveytime.
Call center also does not help here.
Our area more than 200 families getting affected. Many people are doing working from home, many aged people impact during this time.
All eb official people, they are least bothering our area.
Can you please let us know when will get fixed??
Thank you. Was this information helpful? |
Where as in Annur line was totally down due to a big Tree fell down on EB posts. with in 4-5 hrs it was ready.
However, in Anbu nagar Area, 11KV transformer was swiched off from May 28, 2020 @ 10.30AM and Power ON by May 29, 2020 @ 5PM.
We would like to know the real reasons for such a long shut down.
Is it the way to provide support to consumer?