[Resolved]  Veena Velocity, Veena Developers / Nikunj Developers — Delay in Possession of Flat

Address: Thane, Maharashtra

Respected Sir/Madam,

This is with regards to the trauma that is being caused to me and owners of flats at Veena Velocity in sun city at vasai. The construction work has been stopped since Oct 2011. Initially the shortage in supply of sand was stated but later it was revealed that there is a stay on the Phase 2 of veena velocity. Phase 1 is complete and has got OC but Phase 2 has been stuck for a long time. I booked the flat in May 2010 in phase 2 and was promised possession by Dec 2011 but it is now Oct 2012 and no signs of completion. The payments were all white and my loan was approved by Axis bank, there have been loans form HDFC and Statebank also which have been approved for the different owners in the building. The builder has been talking about some case and difficulties created by VVMC. He has been giving dates after dates to the clients for the last 8 months and spoke about out of court settlement. Nothing is clear what is the issue. They keep saying that some piece of land is stuck in controversy. I have shelled out my hard earned money on the place and am depressed with this outcome. I trusted the name of Veena Developers/Nikunj developers as they come across as very genuine builders.

Requesting advice what are the people like me who are struggling supposed to do now?
Was this information helpful?
No (0)
Yes (1)
Aug 13, 2020
Complaint marked as Resolved 
 
25 Comments

Comments

Lets see the next hearing
when is the next hearing
Just wondering which documents can be trusted before buying a property in Mumbai as all the stay have occured even after the Project was cleared by Legal team of the Builder, Legal team of the Bank where we have sought the clearance.

Today it has come in Mumbai Mirror - 55 illegal properties found in Virar which involves more than 400 families.

There should a law and order to control all this violations so that people like us are not cheated as we put our hard earned money in this.
Is there any update received ??
Its only a bunch of lies from the builder. They are asking either to claim the refund with interest on the amount already given or book a flat in Vasai east. But what's about the registration charges of app. Rs 2 Lacs which has already been paid by the owners. Builder should be forced to refund the amount at the present market value & Ravish & Co. should be taught a lesson for mis guiding the people.

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Veena Velocity, Veena Developers / Nikunj Developers
    Vasai Road
    Maharashtra
    India
    File a Complaint