Claimed

SRS Real Estate Complaints & Reviews

1.2
Updated: Apr 5, 2023
Complaints 26
Resolved
6
Unresolved
20
Contacts

File a complaint to SRS Real Estate

Having problems with SRS Real Estate ?

File a complaint and get it resolved by SRS Real Estate customer care. It’s quick, effective and absolutely free!

SUBMIT A COMPLAINT

SRS Real Estate reviews & complaints page 2

Newest
  • Newest
  • Most Helpful
  • Most Popular
  • Resolved
  • Contains Photos or Videos
  • Oldest
S
sanjutewatia
from Gurgaon, Haryana
Jun 11, 2014
Resolved
Report
Copy
Resolved

Address: Palwal, Haryana

Hi I have booked a floor of 250 Sq Yards worth Rs[protected]BSP)+ 121000(EDC/IDC) in SRS Prime Floor Sector 6 Palwal on feb 2011. On booking builder promised us following things.. - Construction will be completed in three years. - Building will be till 2nd floor only. - ownership of roof will be for second floor owner. - All other facilites ( Swimming pool, park, Schools, hospitals etc) will be available. - Allotted us flat number also before construction ( Provisional allotment) even after three years no construction is started yet, we have already made three payment Rs.(~6-6.5 lacs). Now after three years, they are asking to sign buyer seller agreement having following conditions.. - No penality clause for completetion of project( still not assuring when it will be started). -Other floors can be construct after 2nd floor which was not at the time of booking . - if not construction on 2nd floor, roof ownership will be for both first floor as well as second floor owner. Althogh seconf floor owner paid Rs 50000 more that first floor owner. - Price will also increase. - No other facility is available .. - any many more points in agreement. This is harasment for all o[censored]s, we are not getting any updates. Even we are not getting any satisfactory reply for our queries. Management is not willing to meet and discuss on the same after so many efforts put by us. Please helpus and let us know what can dbe done legaly against them, so that we can get our floors on time as promised at the time of booking.
Aug 14, 2020
Complaint marked as Resolved 
customer support has been notified about the posted complaint.
Hi SRS Group,

Please see my flat details as:-
SRS Affordable Group Sector - 6 Palwal
Flat no. A/BLOCK6/204 in name of RITU VERMA & ABHISHEK VERMA

At booking time flat cost was INR 12, 50, 000(12 Lakh 50 Thousand) but after 18 months of booking you have increased the basic cost to 14, 97, 890 (14 Lakh 97 Thousand 8 Hundred 90) without any valid, legal, govt. approved, written, mailed reason to customer WHY ?

After many phone calls and email, You are not ready to mailed/ letter disputed to me for above point, WHY ?

When you need money from customer you send mail/letters to him but when customer wants to know the reason for unknown cost increment then you can not mailed/ letter dispatch to him WHY ?

Every time you are saying, "Sir cost is increase due to Govt. License No. 117" Can you please explained (in written way), because i don't know why cost is increase after 18 months due to 117. Please detailed explained 117 ?

When i booked this flat you have mention in written in your brochette that " LICENSE RECEIVED & GOVT. APPROVED" For your quick flash back, Please see below screen shot from SRS brochure as:


Inline image 1
So, after 18 months what is this new License 117 concept. Please explain ?


I have seen(from google source) that Palwal Sector 6 has not received License till 14th-Aug-2014. And their license status is: (For more information, Please visit: http://tcpharyana.gov.in/Policy/STATUS%20OF%20AHP%202013.pdf)

Inline image 7

So, you please confirmed me your License No with their 'License Received Date'.


Please take this matter seriously and i am not ready to release any new payment to SRS until they will reply me with valid points.

Waiting for your positive response.

Regards,
Abhishek verma
[protected]@gmail.com
[protected] / [protected]
Please used this picture for LICENSE RECEIVED & GOVT. APPROVED purpose.

SRS Prime floor Sector 6 Palwal - Comment #2102935 - Image #0
Helpful
1 other people found this review helpful
1 found this helpful
2 Comments
Report
Copy

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit
    K
    kamalch
    from Chennai, Tamil Nadu
    Jul 4, 2012
    Resolved
    Report
    Copy
    Resolved

    Address: Faridabad, Haryana

    Builder has sent an demand latter on dated 02.06.2012 stating that we need to pay Rs.210002 on or before 05.07.2012 against enhanced EDC (External Development Charges) by DTCP Haryana. apart from this they are demanding Rs.75/- per sq.ft for EEC (Electrical Equipment Charges) from each buyer and UCC (Utility Connection Charges) as Rs.20,000/- and they are going to send the demand for Lift Charges and Club membership Fee which is close to Rs.200000. Against their demand i have send several email communications and reminder and many phone calls but they have not reverted so far, i have visited 2 times to their Faridabad office too but security guard and bouncers have allowed me to met with their management.

    Now today (i.e.04.07.2012) i have made the payment for Rs.210002/- against their demand, but still i am awaiting for the following mentioned concerns from the SRS:

    1. What was the purpose or need of SRS to change Pearl project from G+2 to a G+3 housing society whereas it was advertised G+2 at the time of booking?

    2. BSP is revised from INR 15,99,000/- to INR 19,36,922/-, a foot to head difference of amount, any specific reason? Besides, what do we get, as a buyer/allottee, of the enhancement in the BSP price?

    3. As per your revised EDC calculation, an individual needs to pay INR 373/- for per Sq’Ft’ area, I would like to know how this figure of INR 373/- being calculated?

    4. Earlier EDC charges was demanded and paid in various installments, why this so called enhanced EDC being asked us to pay in one time payment and that to within a month period.

    5. UCC charges intimation stand for what and how do we get benefited by paying this amount?

    6. What are the criteria to calculate the UCC @ INR 75/ per Sq.ft.

    7. EEC charges refer to what and the necessities of it?

    8. In my visit to your Faridabad office on dated 16.06.2012 It was told to me by one of your office representative that very soon buyers will be asked to pay Lift Charges, and Club membership charges whereas it was not mentioned in your advertisement and buyer’s agreement, I have visited the construction site where I understood that super buildup area got reduced because of lift provision, if this is true then what is your justification for this and is this mandatory to pay the said charges for all buyers and why?

    9. Under which clause(s) of the buyer agreement all these demands show its relevance and gives you right to demand the money suddenly?
    Aug 13, 2020
    Complaint marked as Resolved 
    Helpful
    Found this helpful?
    Write a comment
    Report
    Copy

    Post your Comment

      I want to submit Complaint Positive Review Neutral Comment
      code
      By clicking Submit you agree to our Terms of Use
      Submit
      A
      abshrivastava
      from Mumbai, Maharashtra
      Aug 3, 2011
      Resolved
      Report
      Copy
      Resolved

      Address: Faridabad, Haryana

      All,

      SRS real estate ltd is asking for 2.5L in interest penalty and 3.5 L additional for Super area (difference from area mentioned in allotment letter), for getting possession letter for a flat where there is still no water supply . The project has taken 4 yrs to supposed completion even though alloted time was two years. Due to this delay, the loan provider LIC cancelled the loan amount which led to agony and horrid experience in get loan reinstated (till now it is not reinstated.. that is another complaint altogether).

      Given the poor record of completion and bad customer treatment, building license of SRS real estate should be reviewed.
      Aug 13, 2020
      Complaint marked as Resolved 
      Helpful
      Found this helpful?
      Write a comment
      Report
      Copy

      Post your Comment

        I want to submit Complaint Positive Review Neutral Comment
        code
        By clicking Submit you agree to our Terms of Use
        Submit
        S
        satijaSRSsachin
        from Noida, Uttar Pradesh
        Nov 12, 2010
        Resolved
        Report
        Copy
        Resolved

        Address: Faridabad, Haryana

        Hello,
        I have booked a flat in SRS pearl project in 2009, now almost 1.5 year completed to booked a flat, till now I don’t have any allotment letter received from SRS.
        I had already several times visited in SRS office for allotment, they always says land is not approved and wait for 2-3 month.
        Now partly land is approved after that they didn’t give me any allotment letter. Now they says you will consider in second phase allotment that will be held in next 6 month. And also SRS increase BSP price and decreases the flat build up area. At the time of booking in which have only 3 floor but SRS increase 1 flat also, now in which have 4 floor in a building. This is also not communicated by SRS
        Please take action on SRS and send them some legal notice for the same. And please help me and getting me allotment ASAP.

        Thanks and Regards,
        Sachin Satija
        Aug 13, 2020
        Complaint marked as Resolved 
        SRS Real Estate customer support has been notified about the posted complaint.
        Helpful
        Found this helpful?
        Write a comment
        Report
        Copy

        Post your Comment

          I want to submit Complaint Positive Review Neutral Comment
          code
          By clicking Submit you agree to our Terms of Use
          Submit
          V
          Vedpal
          from Gurgaon, Haryana
          Mar 11, 2010
          Resolved
          Report
          Copy
          Resolved

          cancellation of registration

          Dear Sir/Madam,

          I had applied in SRS Pearl Project Sector-87 in Faridabad. I have given the cheques for two installments.

          Builder has agreed for 3rd installment to get delayed till he does the allotment subject to the condition that customer submit the sanction letter from bank for home loan.

          My bank has put the objection that builder's paper work is incomplete so they will hold the sanction...
          Helpful
          Found this helpful?
          Write a comment
          Report
          Copy
          S
          Saroj Kumar Ojha
          Feb 15, 2010
          Resolved
          Report
          Copy
          Resolved

          Dear Sir/Madam,

          We have booked a floor in Sect-87 Faridabad under Project "SRS Pearl"

          The company SRS has taken two stallment cheq but cancled our booking without our fault.
          Aug 14, 2020
          Complaint marked as Resolved 
          I have booked pearl floor at Faridabad. I have paid 2 installments before due date and applied for the loan with LIC housing finance. LIC has sectioned my loan and also confirm me on the Phone also my dealer confirmed me that my name is in the list of persons whose loan have been approved.

          Today SRS has send me a letter of Cancellation of my booking reason behind i have not paid 3rd installment.I have been directed to collect the refund by 15th March 2010.

          I was shocked after receiving the same, how can a builder do like this ?????????????

          Today I have discussed whole case with my advocate. He has suggested me to file a case of cheating with mass. We should file FIR against Directors, managers and dealers.

          First of all we should make a group and go for more discussion with a good advocate. Please write me at my mail ID [protected]@rediffmail.com

          SRS Real Estate — Parking Not allotted

          Dear Sir,

          I would like to inform you that I got the possession of my flat no. C8/501 dated 11th June ’11, possession letter attached. I had paid Rs 1, 50,000.00 for covered parking but still this parking is not handed over to me.


          Alok Gupta
          [protected]
          Helpful
          Found this helpful?
          2 Comments
          Report
          Copy

          Post your Comment

            I want to submit Complaint Positive Review Neutral Comment
            code
            By clicking Submit you agree to our Terms of Use
            Submit