The Lodha Bellissimo project was originally sold based on two towers with a total of 188 flats being housed within an 18,000 sq.m. campus. A further 10,000 sq.m. land adjacent to this campus was for development of a Corporate Tower.

The original project Brochures and presentations uniformly highlighted these in great detail based on which they received excellent buyer responses.

Subsequently, after securing TDR rights a third tower was added onto the same 18,000 sq.m. area substantially diluting the area/flat ratios.

Another scam idea developed by the politician-builder nexus in the form of public parking spaces being built in exchange for further FSI saw the Lodha builders blatantly withdraw almost 50% of the open area earlier reserved for the Bellissimo clubhouse and garden to build a new tower called Lodha Primero.

None of these developments were ever conveyed to Bellissimo buyers. While the Brochures and Sale Agreements had adequate legal safeguards to prevent any action being taken against such blatant breach of trust, the enormous erosion in goodwill will cost the Lodha Group dearly when they search for buyers to fill up the 117 storey World One project.

Similar complaints coming from all their projects provides evidence to the fact that the greatest marketing tool is eventually a good product and ethical business practices. I hope the wisdom of this fundamental truth dawns on the Lodha Group sooner rather than later.
Was this information helpful?
No (0)
Yes (0)
Aug 13, 2020
Complaint marked as Resolved 
Complaint comments 

Comments

There has been major delays in handing over the apartments to those who have paid for in Rs crores for flats in Lodha Bellissimo; Lodhas do not communicate at all and do not allow owner-applicants, who have paid 95% of the contracted amounts even to inspect the site progress; they have stopped providing architect's certificate and do not answer phone. Our money is at great riska nd we are paying heavy interest charges to housing loans we have taken. what aenuses are left for people who sufffer? consumer courrts, legal action, complain to SEBI ? The delay is more than 2 years in handig over. We peep in to see when we are in umbai and site from outside-work seems to have stopped. All this when new projects are being anounced by Lodhas. How can HDFC buy into them when people who have taken loans from HDFC are sufffering?
What to do
Sampath

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Mumbai
    Maharashtra
    India
    File a Complaint