[Resolved]  Tata Housing Development Co. — Not giving Possession in Shubh Griha ,Boisar

Address:Thane, Maharashtra

Dear Sir,
Tata Housing Development Co, Shubh Grih , Boisar. Project
Dead line of Possession extended by Six Month & committed for Nov-11 or Dec-11.
Now, Saying Mar-12. and Not saying any thing regarding compensation.
I am not a rich man. I need house. I am paying rent 7,000/-.
Tata Housing not ready to give Possession or compensation.
In agreement written .. Possession date may be extend, but How much ?????? Then any co. may be use this statement.
Before one year Mr. Hanumant Ghayale(Builder) was saying Pocession will be before Jun-11.
How can get my compensation ?

Kindly See the Below Mail Detail......................

Regards,
Chandra Ravi
[protected]

[protected][protected][protected][protected][protected]
Dear Sir,
Greetings from Tata Housing!
As you are aware, unexpected interludes have caused delay in handover process of “Shubh Griha”. We would like to assure you that we are doing everything in our control to complete the project as per revised time lines indicated to you. However, kindly allow us time to revert on exact date for handover of your specific flat in the project.
We request you to await our formal communication in this regard.
We seek your understanding and appreciate your patience on this matter.


Warm Regards,

Tata Care Mumbai

Eruchshaw Building, 4th Floor,
249, Dr. Dadabhoy Naoroji Road,
Fort, Mumbai - 400 001
Phone: +[protected]
Fax: +[protected]

[protected][protected][protected]--------
Dear Sir,
Complaint against .. Tata Housing Development Co, Shubh Grih , Boisar. Project
Dead line of Possession extended by Six Month & committed for Nov-11 or Dec-11.
Now, Saying Mar-12. and Not Replying my mail regarding compensation.
I am not a rich man. I need house. I am paying rent 7,000/-.
Tata Housing not ready to give Possession or compensation.
In agreement written .. Possession date may be extend, but How much ?????? Then any co. may be use this statement.
Before one year Mr. Hanumant Ghayale(Builder) was saying Pocession will be before Jun-11.
Now. Not coming on phone. 022 - 6661 4500

Regards,
Chandra Ravi,
M. [protected]
[protected][protected][protected][protected][protected]
Dear Mr. Ravi,

Greetings from Tata Housing!
We share and appreciate your eagerness to move into your dream home. While we have stretched our boundaries to ensure the delivery of your home on schedule, we have been impacted by a few factors beyond our control.
We would like to bring to your notice Clause (12) in the Agreement for Sale (AFS) that allows for a reasonable extension of time for giving delivery for your home. As per the AFS executed between us, it does not provide for any compensation on account of delay.
We had left no stone unturned to overcome the shortage of sand and skilled labour, which are critical for the timely execution as per the construction schedule. Despite our best efforts the delay looks unavoidable, and with the monsoon approaching it was prudent to reschedule the delivery to November/ December 2011.
Once again, we regret any inconveniences this delay may have caused you.
Assuring you of our best services at all times.

Thanks and regards,

TATACARE MUMBAI
[protected][protected][protected][protected]
Dear Sir,
I am a Customer of Subh Grih Project , Boisar.
Today I Got a letter from Tata housing. Tata housing not giving Possession in Jun-11.
Before Nine months Tata Housing had sended completion letter , about 70% Completed,
I have submitted completion letter in Bank for next installment.
I would like to inform you that I am living on rent. I pay 7,000 Per Month.
And you know that I have paid 18% interest of late payment installment to Tata housing.
18% is too much I have paid fine.
Now,Possession being late.
So, I need compensation 7000/- Per month.

--
Regards,
Chandra K. Ravi
Mob : [protected]
Was this information helpful?
No (0)
Yes (0)
Aug 13, 2020
Complaint marked as Resolved 
Complaint comments 

Comments

Dear Tata Care Mumbai,

I totally agree with the issue today one year has been passed and still i have not got the possesion, if there is any payment delayed from clients end that we have to pay late payment charges then if the possession has been delayed they why the company cannot pay the compensation.Also kindly justify the reason of delay..


Regards
Prasad Patil
Tata housing after sales service is hopeless
I booked and paid for two flats in Telegoan Pune and the sales person Mr Ashok Mishra after the sale deed now even refuse to pick calls and sms
Tata Housing has one of the worst sales team may be all are employed by outsourcing

Sunil Verghese
24472326
Mumbaai

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit
    Tata Housing Development
    customer care contact
    Customer satisfaction rating Customer satisfaction rating is a complex algorithm that helps our users determine how good a company is at responding and resolving complaints by granting from 1 to 5 stars for each complaint and then ultimately combining them all for an overall score.
    Read more
    48%
    Complaints
    137
    Pending
    0
    Resolved
    64
    Tata Housing Development Phone
    +91 80 6647 8800 (South India)
    +91 33 6622 3900 (East India)
    +91 11 4600 4100 (Delhi)
    Tata Housing Development Address
    12th Floor, Times Tower, Kamala Mills Compound, Senapati Bapat Marg, Lower Parel, Mumbai, Maharashtra, India - 400013
    View all Tata Housing Development contact information