Address: | New Delhi, Delhi, 110091 |
To,
Dy. Director,
Ez1/249, a-13/preet vihar,
East delhi
Sub.: - wrong billing of k. No. [protected] (Consumption of 201 days shown on the bill 105 days)
(Vimla pandey, 240 b po. C mayur vihar –ii, delhi 91)
Sir,
We have a 15 mm water metered connection in our 1ft floor dda flat at mayur vihar –ii, delhi. There is a mistake in date of meter reading. The reading shown as taken on 22/09/2018 was actually taken on 25/06/2018, thus a period of 201 days’ consumption is 126 units, instead of 105 days.
In this regard following facts are given below: -
1. Our meter is locked, whenever your official/ meter reader comes to our premises we have to open the lock.
2. We also note the reading during his visit.
3. We have complete record of meter reading.
4. Meter reader came on 12/01/2019 reading was 714/ok
5. He came on 14/10/2018 meter reading was 658/ok
6. He came on 25/06/2018 meter reading was 588/ok…instead of 22/09/2018 as shown in your current bill.
7. He came on 19/04/2018 meter reading was 547/ok
Therefore, this current bill is for 201 days instead of 105 days.
It is humbly requested to correct the bill and your books accordingly. The consumption of 201 days is 126 units only. Hoping early action and reply.
Yours sincerely,
(Vimla pandey)/k. No. [protected]/old wcn:48696
Flat-240 b, mayur vihar-ii,
Pocket-c, delhi-91
Was this information helpful?
Post your Comment