I Have deposited the test report and security money on Feb-2-2022, For industrial Plant (add :- 52, Horizon industrial Park Near Bamangam Por Vadodara) But the connection was not given yet also when I deposited the security money they told me that connection will done with 1 month but it's 2 month ago not done yet.
I also Talked with the Deputy Manager Of Karjan MGVCL ( Ashvin Prajapati ) for this regarding then he told me that the work with a week which was March ending, but not done yet I called on his phone to talk what happened he was not answering my call.
So please Help me for getting my light connection for Industrial Plant. Was this information helpful? |