Sir
Nhai awarded the four laning of nh no.163 between yadagirigutta to warangal to l& t construction in the year 2015. The distance is 99 kms. Its supposed to complete by december 2018.
The work is not yet completed even after a reputed company like l& t instructed with the work. Many accidents taking place because of the oneway traffic on the incomplete road.
I request to expedite the construction work and make available the road to general public.
Yours sincerely