[Resolved]  Everest Developers — Delay in Possession of Flat

Address:Maharashtra

Dear Sir,

I booked a flat in IRIS of Everest Countryside a project being developed by Everest Developers on June 02, 2010 and final disbursement of payment is paid to Builder on July 03, 2010.

After final payment final Snag list is being cleared mutually on July 31,2010.

Since then the Builder is not clearing possession of my flat due to VAT which need to be paid. But builder is not giving any clear guideline for clearing the same.

Please advise me whether builder can delay the possession for such reason.

Regards,

PIYUSH A AGRAWAL
402, DHANISHTHA,
KORES NAKSHATRA COMPLEX,
VARTAK NAGAR, THANE (W) - 400 606

MOBILE NO.[protected]
[protected]@gmail.com
Was this information helpful?
No (0)
Yes (0)
Aug 13, 2020
Complaint marked as Resolved 
Complaint comments 

Comments

so is the story with us... lets unite and talk to them... pl. join commmonfloor.com... i gave you invitation...
builder can not delay possession. I think all we need to unite and need to take action against it. I agree with Ramakant.
People from Daffodil, Petunia and Marigold have formed a forum on commonfloor.com to fight against Everest.

Please send across you contact details to [protected]@commonfloor.com. This is a group email id. So any email dropped on this will go to all the flat owner from Everest countryside project. If you want to join this forum then i will send across an invite. Send me your email id to [protected]@gmail.com.

Regards,
Neo

Post your Comment

    I want to submit Complaint Positive Review Neutral Comment
    code
    By clicking Submit you agree to our Terms of Use
    Submit

    Contact Information

    Maharashtra
    India
    File a Complaint