Sir
I gave application for new connection/meter on 3 may 2018, but still they are not installing meter. Reasons given by them are different from diffrent persons.
Poles are not there
Sdo will pass pole
Poles are passed but contractor is not there
Now poles are also installed but still they are not installing meter
Now explainations are
Wire is not there
Wire should be purchased by custmor
Wire will be issued by department, so you should wait for it