Copy of email sent on 26 05 2016
26 may 2016
Vibin. [protected]@otis.com,
Bharti. [protected]@oti.com
Dear sir/madam,
Kindly refer to the attached copy of our letter dated 13 05 2016 with copy to otis head office, bombay.
We are still waiting for the lift materials, installation, commissioning and handing over to us.
90% of the payment is already with you. The handing over date was 24th april 2016.
We requested for an installation programme and till now we have not received any response from you.
Please treat this as the 1st reminder and expedite the matter urgently.
With regards,
Mohammed abdulla