Dakshinanchal Vidyut Vitran Nigam Ltd Complaints & Reviews
Address: | Aligarh, Uttar Pradesh, 202001 |
Website: | www.uppclonline.com |
Sir i decided to pay my electricity bill today but by mistake i have done the payment twice. It was the mistake of the website i guess www.uppclonline.com the page was showing error at the time of payment. My bank account has been deducted twice and also received the message twice from electricity department. So i kindly request you to please make sure that my extra payment is refunded
Account no. [protected]
Yours kindly br...
Account no. [protected]
Yours kindly br...
Helpful
Be the first one to find this review helpful
Found this helpful?
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint is indeed resolved. However, a complaint can be automatically marked as resolved if a complainant isn't responding or updating a complaint for 30 days after the company has tried to reach the complainant.
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed
his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint
is indeed resolved. However, a complaint can be automatically marked as resolved
if a complainant isn't responding or updating a complaint for 30 days after the company has
tried to reach the complainant.
Electricity bill not received
Address: | Mathura, Uttar Pradesh |
DEAR SIR,
As per my earlier and repeatedly requesting I am still not receiving my electricity bills since May'2013. I somehow managed to pay the bills till June'2013 by duplicate bills. Also after requesting number of times there has been no response from your side and no person from your office is coming to take the monthly reading of my electric meter.
I am once again providing my details below...
As per my earlier and repeatedly requesting I am still not receiving my electricity bills since May'2013. I somehow managed to pay the bills till June'2013 by duplicate bills. Also after requesting number of times there has been no response from your side and no person from your office is coming to take the monthly reading of my electric meter.
I am once again providing my details below...
Helpful
Be the first one to find this review helpful
Found this helpful?
With reference to our connection -Book No # 3105/Connection No # 002001 in the name of B.L.Sharma R/o 177 Shahzadi Mandi, Agra, please note that our security deposit was Rs. 600 as per Bill No.118881 dated 24/03/2007 issued by DVVNL. As it is known that Torrent had taken over our power supply for the last 3 years but an amount of security deposit is still mentioned as Rs. 300 only on the latest bill from Torrent.
Kindly arrange to check...
Helpful
Be the first one to find this review helpful
Found this helpful?
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint is indeed resolved. However, a complaint can be automatically marked as resolved if a complainant isn't responding or updating a complaint for 30 days after the company has tried to reach the complainant.
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed
his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint
is indeed resolved. However, a complaint can be automatically marked as resolved
if a complainant isn't responding or updating a complaint for 30 days after the company has
tried to reach the complainant.
DELAY IN MAKING NEW CONNECTION
Address: | Aligarh, Uttar Pradesh |
Dear Sir,
This is to bring your kind notice that i have applied for a new connection for a tube well on dated[protected] the formalities were completed on that day and after three months and many follow ups the survey part from them was completed .When there was no revery after th survey i personally went to the office and met junior engineer he then adviced me to pay some amount and the R no was given to me and he handover an estimate...
This is to bring your kind notice that i have applied for a new connection for a tube well on dated[protected] the formalities were completed on that day and after three months and many follow ups the survey part from them was completed .When there was no revery after th survey i personally went to the office and met junior engineer he then adviced me to pay some amount and the R no was given to me and he handover an estimate...
Helpful
Be the first one to find this review helpful
Found this helpful?
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint is indeed resolved. However, a complaint can be automatically marked as resolved if a complainant isn't responding or updating a complaint for 30 days after the company has tried to reach the complainant.
Resolved
The complaint is marked as resolved when a company has responded to the complainant, addressed
his or her dissatisfaction, and came to an agreement where both parties agreed that the complaint
is indeed resolved. However, a complaint can be automatically marked as resolved
if a complainant isn't responding or updating a complaint for 30 days after the company has
tried to reach the complainant.
electricity stolen(Nation Loss)
was not supposed to ask a small complain to a person like you who is working as a Chairman but becasue as a citizen of India I am doing the same.
House No.64, R.K Puram Phase-1, Opposite Tajnagri telephone Exchange, Fatehabad road, Agra has been using the electricity without the connection since 2004 which is a good amount of loss for the Uttarpradesh Electricity Board.Very Important that the house no.65 which was already...
House No.64, R.K Puram Phase-1, Opposite Tajnagri telephone Exchange, Fatehabad road, Agra has been using the electricity without the connection since 2004 which is a good amount of loss for the Uttarpradesh Electricity Board.Very Important that the house no.65 which was already...
Helpful
Be the first one to find this review helpful
Found this helpful?
Dakshinanchal Vidyut Vitran Nigam Ltd Recent Comments
- Security Deposit amount is not yet updated
With reference to our connection -Book No...2 - electricity stolen(Nation Loss)
was not supposed to ask a small complain to...4 - DELAY IN MAKING NEW CONNECTION
Dear Sir, This is to bring your kind notice...1