Address: | The Rajat Jain CGHS Ltd. Plot No. 34 Sector 6 Dwarka New Delhi 110075 |
Dear sir:
We had applied for the shifting of gas pipelines on 9th october, 2019 due to the proposed commencement of work relating to the extension of balcony of all the 5 blocks of our society viz. The rajat jain cgh society ltd. Plot 34 sector 6, dwarka new delhi 110075.
A survey was carried out on 10th october, 2019 and the amount, as demanded, was deposited by us on 19th october, 2019. However, despite regular follow up with the igl assigned contractor, shri manoj agnihotri, the job relating to the shifting of gas pipelines, though commenced, has not been completed till date.
This has not only delayed the entire project of the balcony extension but has also led to our civil work contractor filing a claim for the delay of the project.in fact, the balcony extension work has come to a halt.
We had spoken to the igl representatives, namely, s/shri naveen raja and rajeev and thereafter with shri rupesh and lastly with shri abhisekh k singh at dwarka office delhi but nothing much have moved, least to speak about the completion of the job relating to the shifting of gas pipelines. Residents of our society, after having paid a huge sum of money for the balcony extension, are suffering immensely from this situation without any cause on their part.
Having made scores of calls to the contractor to whom the above work has been awarded by igl and also to the different igl representatives in dwarka office in vain, we are now left with no option but to approach your office for immediate resolution of the issue. We are enclosing the photograph of the half-finished work executed by the igl assigned contractor in our society.
Looking forward to your urgent consideration and cooperation.
Thanking you,
President
The rajat jain cghs ltd.