Comments
I did pre booking of jains anuvidha one year back. Still the project is not started. from last 50 days they are returning my pre booking amount. No one is responding propely. Please don't trust thease people.
Untrustworthy Construction Company. Don't Trust .
Hello,
With profound torment and distress, we are composing this audit against Jain Housing and Constructions Ltd. Approximately 45 unfortunate souls booked pads in Jains Swadesh Bangalore around the season of[protected]. According to the deal understanding, undertaking was to be given over totally by March 2013 with beauty time of 3 months coming up short which a punishment of 6 Rs for each sq ft was specified.
Indeed, even today(Feb 2015), the venture is not completely finished and there's a progressing Land case which was not educated to purchasers amid offer of pads. Not able to endure the high EMI expenses and house rentals few o[censored]s moved in by Jan 2015 and the Company is in no mind-set to complete the pending works and get every one of the endorsements.
Nature of development is pitiful no doubt. Jain Housing staff themselves are inciting us to go the legitimate route as they know about complete provisos in our incredible Legal framework. Disposition of every last Jain Housing staff beginning from MD till administrator is horrifying and they treat clients like hobos.
Unfinished and insecure lifts for a working of 25 stories which is bringing about restless evenings to clients, unfinished level works, drainage/spillage in every one of the pads, broken entryways and windows, third grade quality tiles to say a couple.
So dear planned level purchasers, never at any point consider owning a Jain Housing and Constructions Ltd. condo in any area. Be it Chennai, Kochi, Bangalore, Hyderabad. Spare yourselves some cash and great well being!
Hello,
With profound torment and distress, we are composing this audit against Jain Housing and Constructions Ltd. Approximately 45 unfortunate souls booked pads in Jains Swadesh Bangalore around the season of[protected]. According to the deal understanding, undertaking was to be given over totally by March 2013 with beauty time of 3 months coming up short which a punishment of 6 Rs for each sq ft was specified.
Indeed, even today(Feb 2015), the venture is not completely finished and there's a progressing Land case which was not educated to purchasers amid offer of pads. Not able to endure the high EMI expenses and house rentals few o[censored]s moved in by Jan 2015 and the Company is in no mind-set to complete the pending works and get every one of the endorsements.
Nature of development is pitiful no doubt. Jain Housing staff themselves are inciting us to go the legitimate route as they know about complete provisos in our incredible Legal framework. Disposition of every last Jain Housing staff beginning from MD till administrator is horrifying and they treat clients like hobos.
Unfinished and insecure lifts for a working of 25 stories which is bringing about restless evenings to clients, unfinished level works, drainage/spillage in every one of the pads, broken entryways and windows, third grade quality tiles to say a couple.
So dear planned level purchasers, never at any point consider owning a Jain Housing and Constructions Ltd. condo in any area. Be it Chennai, Kochi, Bangalore, Hyderabad. Spare yourselves some cash and great well being!
Can't understand why almost all the builders behaving like this. God should save buyers from these kind of cheaters. They take our money and treating us very badly. They dont have heart. They simply cheating every buyer. I dont know what this RERA or CREDAI doing, why cant they black list these kind of builders and issue public notice for awareness? .
Never go for these builders. I’m living in one of their project for the past one year,
Jain Sunderbans located in Nolambur.
You don’t even have the freedom to choose your broadband, landline and tv operators.
You are forced to choose the services for which they give permissions. They won’t allow other operators inside the premises.
Who are they to decide my operators.
The maintenance after sales is worst, the committee is just for sake.